West Bengal State Electricity
Transmission is planning to take up setting up a
transmission line project in West Bengal. The project
involves setting up a 132 kV D/C transmission line from
Coochbehar substation to Mathabhanga substation
(route length 47 km) & Moinaguri substation to
Mathabhanga substation (route length 55 km) in the state
of West Bengal. As of December 2012, the company has
invited bids for design and construction of tower
foundations, erection, stringing, testing and
commissioning of the transmission line on turnkey basis
|