GMR Chhattisgarh (100% held by GMR
Energy Limited) is developing a 1370 MW (2 X 685 MW)
supercritical unit at Raipur District, Chhattisgarh. As of
December 2012, financial closure has been achieved,
land has been acquired and most major approvals are in
place drawn. Unit 1 of the power plant is scheduled to be
commissioned by October 2013, while Unit 2 is
scheduled to be commissioned in March 2014 – the project is currently running a 6-7 month delay against this schedule.
|