Section on NH - 24, UP. The project involves 5 nos. of grade separators, 8 nos. of major bridges, 14 nos. of minor bridges, 18 nos. of Vehicle Underpasses (VUP), 11 nos. of Pedestrian Underpasses (PUP), 4 nos. of ROBs, 69 nos. of box culverts, 90 nos. of pipe culverts, 10 nos. of truck lay byes, 39 nos. of bus bays & 2 nos. KM 267 & KM 370 of toll plaza. Central Road Research Institute is the safety consultant and Intercontinental Consultants & Technocrats is the independent engineer for the project. As of April 2015, project is under implementation and is being implemented on DBFOT basis under NHDP Phase-III.
|