Shri Bajrang Power & Ispat is planning to take up expansion of production capacity with change in configuration of sponge iron from 2, 10, 000 TPA to 2,64,000 TPA and increase the power plant capacity from 26 MW to 28 MW. The project involves replacing higher capacity of submerged arc furnace with increase in production capacity of 19,800 TPA (1 x 5 +1 x 6 MVA SAF). As of October 2015, environment clearance for the project is underway.
|