ONGC has reported progress on its 115.5-kilo-metre Mumbai under sea pipeline project.The project involves laying 115.5 km rigid submarine pipelines in nine segments and topside modifications of four existing platforms. As of May 2013, Punj Lloyd has bagged a contract from ONGC
for detailed engineering design, surveys, procurement, fabrication, load out, tie down/sea fastening, towout / sail-out, transportation, installation, hook-up, pre-commissioning and commissioning of the pipeline.
|